Competent-person daily inspection for supported and tubular frame scaffolding covering mudsills, plumbness, full decking, guardrails, and scaffold tag status.
Verify scaffold legs rest on level, compacted ground or concrete with proper timber mudsills and steel base plates (never on loose bricks, buckets, or hollow blocks).
Confirm standards are plumb, all cross-braces and locking pins are engaged, and tie-ins to the structure meet the 4:1 height-to-base-width ratio requirement.
Ensure platforms are fully planked with scaffold-grade lumber (no gaps >1 inch), top rails sit at 38–45 inches, mid-rails are installed, and toe-boards are secured.
Confirm dedicated access ladders or stair towers are securely attached (no climbing cross-braces) and maintain at least 10 feet clearance from energized power lines.
Affix or update the Green (Safe), Yellow (Modified/Harness Required), or Red (Do Not Use) tag at all access points with inspector signature, date, and time.
OSHA 1926.451(f)(3) requires a competent person to inspect scaffolds for visible defects before each work shift and after any occurrence (such as high winds, impact, or modification) that could affect structural integrity.
Green means the scaffold is complete and safe for use; Yellow means it has been modified or lacks full guardrails so specific precautions (like 100% fall arrest tie-off) apply; Red means incomplete or unsafe—do not climb.
Pre-shift 360-degree walkaround and cab function check for hydraulic excavators covering undercarriage, boom/bucket pins, hydraulic leaks, and swing alarms.
Mandatory daily pre-operation inspection for tower cranes covering anemometer wind speed, load moment indicator (LMI), anti-two-block, hoist ropes, and slewing brakes.
Daily site-wide personal protective equipment (PPE) audit verifying hard hats, high-visibility vests, eye/hearing protection, and task-specific respirators or gloves.